A Glance at the Future:
The bustling city of Mumbai is witnessing a transformative project that promises to enhance connectivity for the residents of Vikhroli. The ambitious East-West Bridge construction is progressing steadily, overcoming hurdles that have long delayed this vital infrastructure development.
For over a decade, Vikhroli residents have grappled with the closure of the level crossing gate in 2011, disrupting essential east-west connectivity. The ambitious bridge project faced setbacks due to land acquisition issues and the rehabilitation of affected structures. However, recent developments indicate a positive turn of events.
The financial commitment to this critical project stands at Rs 26.68 crore, with equal contributions from the state government and the railways. This collaboration demonstrates a shared responsibility to address the needs of Vikhroli residents for seamless east-west connectivity.
Despite hurdles, the ongoing construction of Vikhroli's East-West Bridge remains on track. Approximately 60% of the physical work has been completed, marking a significant milestone. The bridge, costing Rs 26.68 crore, is a joint effort between the state government and the railways.
Vikhroli has endured 12 years without proper east-west connectivity, forcing residents to take detours to neighboring Ghatkopar or Kanjurmarg. The closure of the level crossing gate in 2011 severed a crucial link for the community. Finally, the new bridge promises relief by mid-2024.
Detailed inspections by the Research Designs & Standards Organisation (RDSO) have approved the completed girder fabrication. Assembly and launching of girders are underway, showcasing significant progress. Safety measures, including road closures, ensure the smooth execution of construction activities.
The ongoing work includes the east-side approach spanning 100 meters for launching railway span girders. Metalizing work is in progress, emphasizing the commitment to quality. At 615 meters, the approaches further contribute to the overall scope of the project.
Local resident and Vice Chairman of the Bombay Catholic Sabha, Mario Jose Rodrigues, expresses optimism after 11 years of waiting. He acknowledges the efforts of MP Manoj Kotak in addressing this long-pending issue and looks forward to the completion of the connectivity bridge by May 2024.
Local resident Mario Jose Rodrigues shares his optimism as the bridge project nears completion. He appreciates the efforts of MP Manoj Kotak in addressing the long-standing issue, bringing relief to Vikhroli residents eagerly awaiting restored connectivity.
Vikhroli's East-West Bridge project signifies more than just a physical connection. It symbolizes resilience, collaboration, and the unwavering spirit of a community eager to embrace a new era of seamless connectivity. EstateUncle is proud to witness and contribute to this transformative project, reflecting our commitment to enhancing lifestyles through strategic real estate solutions.